Polisario invité au Congrès du PP espagnol: Nizar Baraka recadre Feijóo sur la marocanité du Sahara    La Mauritanie dément toute réunion entre son président et Netanyahu    Mehdi Bensaïd : le PAM n'est pas une simple machine électorale    Le régime de Tebboune face au risque de faillite : la chute des réserves de change annonce une crise économique imminente en Algérie    CAN Féminine : le Maroc domine le Sénégal et termine en tête du groupe A    Le karaté marocain s'avance en pionnier vers le trône africain avec la candidature de Mohamed Mouktabil    CAN (f) 2024: Le Maroc QUALIFIE premier du groupe A    Région RSK : un taux de réussite de 93,23% au baccalauréat    Disparition de Medhi Narjissi : La famille poursuit sa quête de vérité en Afrique du Sud    African Security Analysis observe que le Maroc structure sa souveraineté militaire par la technologie et la production défensive    5G au Maroc : L'ANRT lance l'appel à concurrence pour les futurs opérateurs    Tennis: Iga Swiatek gagne son premier Wimbledon en battant Anisimova    CAN Féminine : Le onze de départ de Vilda face au Sénégal    France : Cinq mois de prison avec sursis pour un étudiant pour un piratage pro-palestinien ciblant des étudiants juifs    Achraf Hakimi emerges as strong Ballon d'Or contender after stellar season    Mohammedia : Vers la renaissance du Parc des Villes Jumelées?    Diaspo #397 : Lamiss Amya, la violoniste marocaine qui fusionne techno et racines orientales    Pastilla à l'honneur : Le Maroc décroche la 3e place au concours gastronomique de Washington    Chine : Pékin dévoile un nouveau train Maglev capable d'atteindre 600 km/h    50e session de l'APF: Rachid Talbi Alami et les présidents des parlements participants reçus à l'Elysée    Volkswagen ferme pour la première fois une usine en Chine    Yémen: Le SG de l'ONU condamne la reprise des attaques des Houthis contre les navires en mer Rouge    Gazoduc Africain Atlantique : Réunions à Rabat du Comité technique et du Comité de pilotage    L'indice mondial des prix alimentaires progresse légèrement en juin selon la FAO    Droits de douane: Trump revient à la charge contre l'UE, Bruxelles souhaite un accord    Béni Mellal : L'Intérieur annonce la fin d'un sit-in périlleux et l'ouverture d'une enquête    L'ANEF encadre des travaux forestiers à Al Borj liés au projet électrique Tanger II    Rencontre sino-américaine à Kuala Lumpur : ouvre-t-elle la voie à une désescalade entre Pékin et Washington ?    Un nouveau plan d'action pour les échanges entre civilisations dévoilé lors d'un sous-forum    La trompette nomade d'Ibrahim Maalouf résonne à Casablanca    L'ICESCO renforce le dialogue civilisationnel lors d'une rencontre de haut niveau avec des responsables chinois    Mehdi Bensaïd lance des projets culturels et pose la première pierre du chantier de restauration de Sijilmassa    La cigogne et l'entrepreneur    L'OMPIC participe à la 1ère réunion de l'Alliance francophone de la propriété intellectuelle    REIM Partners investit plus d'un milliard de dirhams dans le premier OPCI dédié à la santé    Dar Taarji dévoile AKAN, une collection singulière de boutique-hôtels de charme    France : Un Franco-Marocain tué après avoir tenté de stopper une violente altercation    Marrakech : L'influenceuse Fidji Ruiz hospitalisée avec son mari Anas après un grave accident de la route    Réseau : Auto Nejma tisse sa toile à Agadir    L'Université d'Aix-Marseille attribue le titre de «Docteur Honoris Causa» à Mostafa Terrab    L'intelligence artificielle, catalyseur de réinvention de l'action publique au Maroc    Algerian Referee Sparks Controversy at Women's Africa Cup of Nations After Removing "RAM" Logo    Les prévisions du samedi 12 juillet    Euro féminin 2025 : Hier, l'Espagne et l'Italie qualifiées, ce soir duel pour la première place entre l'Allemagne et la Suède    Gouvernance des données : Pilier négligé de notre stratégie digitale ? [INTEGRAL]    Chambre des représentants : adoption en commission du PL portant création de la "Fondation Maroc 2030"    La Chine à mes yeux: un concours ouvert aux Marocains pour découvrir et raconter la Chine    Al-Haouz: 46.650 familles ont pu achever les travaux de construction et de réhabilitation de leurs habitations    







Merci d'avoir signalé!
Cette image sera automatiquement bloquée après qu'elle soit signalée par plusieurs personnes.



Post-earthquake reconstruction efforts in Morocco slow-paced, report laments
Publié dans Yabiladi le 17 - 02 - 2025

The devastating earthquake of September 8, 2023, which struck Al Haouz and its surrounding regions, left nearly 2.8 million Moroccans living in extreme precariousness. In its citizen observation report covering the period from September 2023 to October 2024, Transparency Maroc delivers an unflinching assessment of the management of post-earthquake reconstruction in the affected areas of the High Atlas.
2,946 people were killed, 5,674 were injured, and 2.8 million others in 3,000 villages were affected by the devastating earthquake that struck the High Atlas regions of Morocco on September 8, 2023. Shortly after the tragedy, the government reacted by mobilizing the Royal Armed Forces (FAR) and other state actors to ensure emergency housing.
Temporary relocation arrangements were put in place—an effort praised by some local actors—but since then, the coverage and quality of the solutions provided have proven insufficient, according to the annual report of Transparency Maroc. Despite the cold winter and heavy snowfall this year, many victims still have to cope with limited resources and means to protect themselves.
Armed with its stated commitments, the state had announced an Integrated Post-Earthquake Reconstruction Program for the period 2024-2028, with a colossal budget of 120 billion dirhams. This program was intended to cover several areas: housing reconstruction, infrastructure rehabilitation, improving access to remote areas, and reviving local economic activities. However, Transparency Maroc notes that during the first year, public action fell short of expectations and stated promises.
An ambitious reconstruction program poorly executed
One of the main shortcomings of the Post-Earthquake Reconstruction Program is the abnormally slow pace of reconstruction. One year after the earthquake, disbursement rates remained very low—22% for the third tranche and just 3% for the fourth tranche of the program—while ongoing delays at construction sites continued to hinder the effective delivery of aid. Added to that, the high inflation of construction materials and transportation costs heavily weigh on the realization of projects.
The government quickly adopted several legislative texts and decrees to manage the crisis. The creation of the «Special Fund for the Management of Earthquake Effects» (Fund 126) and the establishment of the High Atlas Development Agency (ADHA) were among the key measures. However, the ADHA, which was supposed to serve as the operational body responsible for implementing the program, was still not fully operational more than a year after the earthquake. Its Director General was only appointed in October 2024.
The report also highlights the absence of a participatory approach. Strategic decisions, made within a few days in urgency, do not seem to have integrated consultations with local actors and the affected population. This lack of consultation contributes to a disconnection between the announced measures and the realities on the ground, increasing the frustration of the victims.
Opacity and reduced access to information
Another major point of Transparency Maroc's criticism concerns the transparency of public action. Data related to budget management—though presented as overall figures—remains opaque and difficult to verify. The observatory deplores the lack of regular publication of detailed reports on the use of allocated funds, preventing citizens from accessing information. This communication problem fuels a sense of injustice among the affected populations, who are often left unaware of the disbursed amounts and the criteria used for allocating aid.
Beyond the figures and administrative delays, the report highlights the dramatic social impact of the earthquake. The slow pace of reconstruction has sparked a protest movement among the victims. Beyond material hardships, the consequences for education and healthcare are deeply felt. Promises to relocate thousands of students and rehabilitate school facilities have not been fulfilled, leaving the 2023-2024 school year in these areas as a «lost year», particularly for middle and high school students. In the healthcare sector, the lack of operational facilities in the affected areas exposes populations to heightened risks.
Finally, the report laments that the reconstruction process is largely being carried out using concrete, contrary to royal directives advocating for buildings that reflect the region's heritage. According to official assessments, the road rehabilitation program is progressing, particularly on Road N7, thanks to funding from Fund 126.
However, the Observatory has been unable to verify this data through the public procurement portal. Additionally, the distribution of direct aid has been generally successful, despite complaints about the remoteness of bank branches and high transfer fees. To date, the disbursed budget amounts to 1.7 billion dirhams.
In conclusion, the citizen observation report, based on official documents and field testimonies, calls for a reevaluation of governance mechanisms and a more transparent, participatory approach to mobilization.